We commenced and completed a very tight programme of works on behalf of Red Tree at Cheadle Hulme Medical Centre, from Start on site to completion our works were completed within 2no days and included the plaining off of 1,600m2 of existing Tarmac surfacing, adjustment of ironworks and the Machine-lay of new Tarmac surfacing x 1,600m2 we also completed all White-lining incorporating new Disabled parking bays and the like.

Our works had to be completed and handed over to our client so as that the medical centre could be in operation on Monday 11th May at 8.00am this way minimising any disruptions that could have been caused if these works were carried out in normal working hours and also minimising any interfacing with the public, all works completed to 100% satisfaction of all concerned. Contract Value £23,000