White Moss Youth Club

Client: 
Cruden Small Works

This project involved the construction of a Multi Use Games Area (MUGA) pitch at a community youth centre in Blackley, Manchester. This entailed the design and installation of a land drain, which drained into a SUDS (Sustainable Urban Drainage System), and the construction of a concrete edged permeable tarmac pitch.

The whole pitch was surrounded by new mesh fencing and gates which incorporated new basketball posts and goal mouths. This project was completed to a very challenging programme, from commencement on site to handover was just 15 working days.

Byrne Civil Solutions Ltd worked closely with the main contractor for this project, making design recommendations and supplying all material and labour resources to complete the project.